Featured Article I

Saving the World One Project at a Time: Planning by the Numbers

By: Jim Mayes (IT Metrics Strategies, Cutter, December 2000)

"Your history will help you better manage the future."  -- Michael Mah [1]

Recently, as I described a software project risk assessment that I had done, Michael Mah remarked rather facetiously: "Jim, you're just saving the world, one project at a time!"  I may not be "Saving the world before bedtime!" as the "Powerpuff Girls" do, but I do believe that project level metrics, when applied to project planning, can have a significant impact on the outcome of individual software projects.  "Planning by the Numbers" (PBN) actually illustrates how the principles outlined in Michael Mah's ITMS article "Sizing Up Your Promises and Expectations" [1] can be put into practice.

PBN is the concept of using historical project level metrics to aid the project manager (PM) in discovering facts about software projects.  While not as simple or cookbook as "painting by the numbers", the PM with support from a Metrics Specialist, can use this information for project planning, validation, and risk assessment.  In many ways I do believe that the Metrics (or Estimation) Specialist performs the role of "Chief Memory Officer"; that is, someone who remembers the past, so that we can avoid the same mistakes in the future. [1] As a software development manager, I became interested in software metrics for providing decision support information related to my projects.   Software metrics provide many benefits for such things as managing outsourcing contracts, process improvement, productivity benchmarking, and balanced scorecards; however, you would be missing one of the greatest benefits, if historical software metrics were not used for making decisions and planning projects. 

The analysis of project level data has taught me some lessons over the years, which I will share. All of this analysis was done using QSMís SLIMtm tools.  This includes the primary components of the PBN process, which are to:

         1.  Collect, slice and dice internal historical project data

         2.  Normalize the software project data for comparison

         3.  Trend the data

         4.  Analyze the data to discover facts

         5.  Use the analysis results for planning software projects

Collect, Slice, and Dice the Data

To begin with, data must be collected for internal historical projects.  This can be done via a productivity benchmark [2, 3] or this could be accomplished by less formal methods; however, the data must include the SEI CMM core measures of size, effort, schedule, and defects [1].  Data consistency is the key to having a good decision support database.  In order to insure consistency, document the rules in a data dictionary.  Also, when building an internal historical project repository, the project data points should be categorized.   Allow for enough stratification such that apples to apples project comparisons can be made if needed; such as, project type, environment, user organization, development organization, language, etc.

Next, the Metrics Specialist needs a "slicer and dicer," with the capability to extract and analyze the data statistically.  This can be accomplished using software metrics tools such as QSMís SLIM-Metricstm and DataManagertm.  Specific project data can be compared to the entire database, specific subsets of data, or both.  Ideally, if you have access to industry data (QSM, IFPUG, etc.), benchmarking specific project data against industry data is also beneficial as an additional decision point.  However, the benefit of having internal historical project data cannot be overemphasized. 

Normalize the Data

One of my metrics discoveries was the importance of normalizing project size data for statistical trending.  This is not to argue the merits of Source Lines of Code (SLOC) versus Function Points (FP), since I use both measures.  However, my objective is to describe how I have been using these measures, continuously improving the results as I refined my techniques by using discovery metrics. [7] There is no perfect software sizing measure; therefore, I use the best aspects of both the SLOC and FP measures, which in my opinion achieves better results, as long as you use consistent counting methods.  I primarily use FP's for sizing project estimates.  Because FP's reflect the user view of a software project, a FP count can be accurately determined based upon the software requirements.  As the project requirements change, the FP count can be updated to reflect changes in project size.

I first tried using Function Points as the size component for statistically trending historical project data.  However for this purpose, I discovered that there is not a strong convergence of data, unless the project size values are normalized based upon programming languages and code mix. Therefore, I convert FP's to SLOC.  This can be done using Industry Factors such as those provided by SPR (Capers Jones) or as illustrated in the September 2000 issue of ITMS [1], but preferably you should use SLOC/FP factors that have been internally calibrated.  I have also found that it is important to normalize project size, in relation to the effort required to produce the code (new, modified, reused, tested, etc.), for determining the productivity rate to use for a project estimate.

In the early 1980's, Robert Tausworthe of the Jet Propulsion Laboratory of the California Institute of Technology, determined a relationship between the effort to develop new code and the effort to modify code.  Basically, the theory suggests that if the effort to develop a line of new code is taken as unity, then the effort to modify a line of existing code is some fractional value.  The values that Tausworthe found on a number of JPL rehosting contracts are shown in Table 1. [4, 5]  I do not always use the full range of Tausworthe factors, simplifying it most of the time to using factors of 1.0 for new/conversion code, and .24 for modified/deleted code (.24 is the average of all of the effort ratios except for "New Code").  Also, if the project involves a substantial amount of regression testing, as is the case with COTS (Commercial-Off-The-Shelf) software customization and integration projects, then it is important to apply the "Tested" ratio of .12 as well, to all of the unmodified code.

I apply the Tausworthe factors to the SLOC/FP language conversion factors and not to the Function Points.  This allows a normalized ESLOC comparison for trending a wider range of projects (new development, enhancement, and COTS integration) as shown in the scatter charts later in this article.  It also allows for additional analysis using Function Points, which have not been normalized, for analyzing the cost of the functionality delivered.  Based upon my experience, this is where I believe the distinction lies between using FP's versus ESLOC.  FP's provide a better measure of the functionality delivered, and the related cost of that functionality for metrics such as Cost per FP.  ESLOC provide a better productivity view to be used for estimation, risk analysis, and project data trending.  I am sure that others have their own views on this matter based upon their own experience, just as my views are based upon my experience.  Just make up your own mind as to what works best for you, and that you can substantiate using your own discovery metrics.

This table shows six ways in which existing code can be modified.  For each type of modification the ratio of the effort-to-modify to effort-to-code-as-new is given. Note: The number of lines of code added, changed, and deleted are subsets of the number of lines reused.  Therefore, their sum must be less than or equal to the number of reused lines. [5]

Type of Modification

Effort Ratio

New Code:  subject to entire development process

1.0

Reused:  the lines of code in modules that will be reused, but will be modified by additions, changes and deletions.

.27

Added:  the lines of code to be added to reused modules.

.53

Changed:  the lines of code in the reused modules to be changed.  This effort is typically less than the effort to add lines.

.24

Deleted:  the lines of code to be deleted (line by line) from reused modules

.15

Removed: the lines of code to be removed in modules or programs as whole entities.  Testing must takes place to check reused modules that interface with the removed modules.

 

.11

Tested:  the lines of code from the unmodified but reused modules which required no modifications but still exist and require testing with new and modified software.

 

.12

Table 1: Software Project Size Normalization Effort Ratios

Trend the Data

For longer than I care to admit, I used averages for productivity calculations related to software project estimates.  Then as I began benchmarking my estimates against project data trended for size, I noticed a great disparity related to the project productivity averages and the project size trends. 

For example: As shown in Figure 1, I selected data for 19 projects from my repository, similar to the project that I was estimating.  (NOTE: The charts and values used in this article are for illustrative purposes only, and are not related to any specific data set; however, they are based upon actual findings.) The average productivity rate for these 19 projects, using the QSM Productivity Index (PI) scale, was 12.9.  When I plotted my project estimate on a productivity graph trended for size, I noticed that the average productivity was 33% lower than it should have been for a project of that size.  The 3 project projects (A, B, and C) highlighted on Figure 1, of similar size, type, and the same development team, had a average PI of 19.1. Therefore, I used the trended PI of 19.1 for my estimate instead of 12.9.  It was still an average, but it was a trended average.

There are many reasons why project size affects productivity. One reason is that there is a smaller percentage of effort allocated to overhead for larger projects than there is for smaller projects.  Larger projects also usually take longer, which is also a factor, due to the effort/schedule ratio.  However, there is a limit that is reached where bigger projects are no longer better, and there is an optimal effort/schedule ratio, as we learn in the following section.

Figure 1: Using Trended Data Relative to Project Size

Analyze to Discover Facts

Data analysis can be very enlightening and exciting as we discover new information.  We can discover the answers to such questions as, How can we get more "bang for the buck" from our software projects?  How do we increase business value? How do we staff our projects relative to schedule, in order to optimize the business value?  With regard to the first two questions, one of the ways to do this is to increase productivity.  Therefore, we may want to discover the effect that project size has on productivity.  This can be analyzed and illustrated as shown in Figure 2. 

The trend shown in Figure 2 illustrates the "Bell Shaped Curve" that I discovered in relation to project size versus productivity.  The data is on a log-log scale, which causes the trend lines to appear linear.  However, you will notice that the data points form a curve represented by the dashed line that was added to Figure 2 to reflect this tendency.  As the size increases, the productivity increases; however, it reaches a size where productivity starts declining.  Specifically, prior to the 30K ESLOC mark, the data points consistently trended upward, then they leveled off.  After the 150K ESLOC mark the data points displayed an overall downward tendency.  With this analysis, I discovered that the projects sized between 30K and 150K ESLOC provided the best "bang for the buck" and business value.  This size range also has the highest convergence of data points within +/-1 SD.

Another fact that we may want to discover is the optimal relationship between effort and schedule associated with the projects in the optimum size range.  Using the Putnam Manpower Buildup Index (MBI) scale, where MBI = Total Effort/(Development Time)3 [5, 6], Figure 3 illustrates how we can analyze the appropriate ratio of effort to schedule.  The MBI is a measure of schedule compression where projects with lower MBI's are less compressed than projects with higher MBI's, and less compression equates to a lower cost and higher quality.  In this case, using internal project data, the optimum MBI is in the 4 to 6 range. The MBI also seems to converge more for the projects in the optimum size range.

Figure 2: The Bell Shaped Curve Related to Project Size and Productivity

Figure 3: Analyzing Optimal Effort/Schedule Ratio Using Putnam MBI Scale

Use the Results for Planning

The primary benefit of PBN is for project planning.  We can put to use the information that we learned during data analysis for developing software release strategies, determining whether estimates are reasonable, and for risk assessment.  The PBN process supports the use of trended data for this purpose. When I prepare a project estimate for an internal project or validate a vendor estimate, I want to see how it compares to the historical project data trends.  For example: I had a client tell me that my estimate seemed high for a 250K ESLOC project; however, when I plotted the data point on a trend chart it was within the ballpark for a project of this size.  In fact, the cost was right in the middle of the trend.  Therefore, the client was much more inclined to accept my estimate.  This concept would also apply to a vendor estimate that was being validated in this manner; such that if the vendor cost was in the high range on the chart, it could be considered unreasonable.  Estimate validations and risk assessments are done in much the same way.  The following examples illustrate how the PBN concepts are used for project planning; specifically, Example 1 illustrates planning software releases, and Example 2 illustrates estimate validations and risk assessments:

Example 1 - Project Planning: Strategy Analysis

Figures 4 and 5 compare monthly versus bi-monthly release strategies for an internal client.  These illustrations were used for encouraging the client to consider alternatives that would provide greater business value.  Table 2 documents the results of this analysis, which indicate that for the same yearly cost (effort) and a 35% longer schedule per release, that the yearly code output can be increased by 267% and the quality by 75%, just by changing from monthly releases to bi-monthly releases.  The quality improvement is significant  since it reduces the resources required for error correction between releases.  Notice that the bi-monthly release strategy uses a project size within the optimal size range illustrated in Figure 2, and that the MBI is in the optimal MBI range illustrated in Figure 3.

Release Strategy Analysis

Assumptions - Monthly Releases (Figure 4)

* Monthly releases are based on an average of historical small releases; i.e., 5.2 months duration, 6,000 ESLOC, 6.7 MBI, 47 Staff Months (SM) of effort, .63 Mean Time to Defect (MTTD), including the Planning, Analysis, and Main Build Phases.

* Illustrates 12 monthly releases that complete during a calendar year.

Assumptions - Bi-Monthly Releases (Figure 5)

* Bi-monthly releases are based on an average of historical larger releases; i.e., 7 months duration, 44,000 ESLOC, 5.4 MBI, 95 Staff Months (SM) of effort, 1.1 Mean Time to Defect (MTTD), including the Planning, Analysis, and Main Build Phases.

* This illustrates 6 Bi-monthly releases during a calendar year

Conclusion

Six Bi-monthly releases during a calendar year could produce 267% more code than 12 Monthly releases, same yearly effort/cost, 35% longer schedule per release, & 75% better quality:

* Twelve Monthly Releases produce 72,000 ESLOC and require 564 SMís of effort.

* Six Bi-monthly Release produce 264,000 ESLOC and require 564 SMís of effort.

* Individual Bi-monthly Releases are 7 months duration each, versus 5.2 months each for Monthly Releases

* MTTD (at deployment) for each Bi-monthly release is one defect every 1.1 days, versus one defect every .63 days (1.6 defects per day) for each Monthly release.

Table 2: Release Strategy Analysis (Figures 4 and 5)

 

Figure 4: Release Strategy Analysis - Monthly Releases

 

Figure 5: Release Strategy Analysis - Bi-monthly Releases

Example  2 - Project Planning: Estimate Validation and  Risk Assessment

This example is divided into two parts, illustrating how estimate validations and risk assessments were performed for the SRO and GPA projects.  But first, it is important to understand the concepts of validation and standard deviation.  Validation is the concept of assessing the reasonableness or risk of an estimate, using trended historical project data.  The same concept would apply when validating an internal estimate or a vendor estimate. [8] With both validation and risk assessment we use the statistical trending measure called standard deviation (SD), which is the measure of variation equal to the square root of the variance.  Figure 6 shows the percentage of projects that would be within the SD trend lines; that is, +2% (+3 SD), +14% (+2 SD), +34% (+1 SD), -34% (-1 SD), -14% (-2 SD), and -2% (-3 SD).  Therefore, roughly 68% of projects are within +/-1 SD, 96% are within +/-2 SD, and 100% are within +/-3 SD.  Average values fall on to the "mean" or center trend line.  The values outside +/-3 SD would normally fall within what Putnam and Myers call the "Impossible Zone" [5, 6].

When estimates are plotted for validation and risk assessment as shown in Figure 6, projects within the +3 SD would have a value higher than 98% of the projects being compared.  Likewise, project estimates within the -3 SD range would have a value lower than 98% of the historical projects; +2 SD would be higher than 84%; -2 SD would be lower than 84%; +1 SD would be higher than 50%; and -1 SD would be lower than 50%.  These values are usually best compared on a log(x) size-linear(y) scatter chart, depending on the data set size and value range.  Project estimates within the +/- 3 SD range could be considered extremely high or low risk depending on the values being compared.  Likewise estimates that fall within +/- 2 SD could be considered high risk.  Estimates falling within +/- 1 SD would stand the highest probability of success depending on how close to the mean line they fall.  Another factor would also be how the estimate compares to projects of same size, type, and development team, plotted on the trend chart.   

SRO Project Validation and Risk Assessment

Figures 6, 7, and 8 illustrate the risk assessment of an estimate based upon customer-constrained requirements and schedule.  This was done to validate concerns of the development team, determine the project's viability, and illustrate the risk to the customer.  The data points and trend lines shown in Figures 6, 7, and 8 are based upon projects similar to the SRO project.  Also, three projects (D, E, and F) of similar size and type are highlighted, which were previously completed by the development team assigned to the SRO project.  The data analysis indicated that the productivity required to complete the project, as constrained by the customer, would be 39% higher than achieved on the 3 similar projects completed by the development team.  Also, Figure 6 shows that the estimate falls within the +2 SD range; i.e., a production rate of higher than 84% of all similar projects must be achieved.

Figure 7 shows that the Main Build Phase (Detailed Design, Construction, and Testing) must be completed faster than 84% (-2 SD) of all similar projects, and 81% faster than the three highlighted projects completed by the development team.  This is also confirmed in Figure 8, which illustrates that the SRO project estimate MBI of 9, is higher than 84% (+2 SD) of all similar projects and 34% higher than the highlighted projects. This indicates that the project has an extremely compressed effort/schedule ratio.  All of the analysis results illustrate that the project is high risk; however, as the saying goes, "The greatest risk, is not taking one." In this case, the project had to be done.  The difference is that with the results of this analysis, the customer and the PM were now in agreement as to the risk, and could plan strategies for mitigating and managing the risk.

If you or the customer choose to accept the challenge of a high risk project, it is best to know what you're in for, so that you don't wind up in the "impossible zone".  If at all possible, it is best to plan projects such that the project values fall within +/-1 SD, in order to allow some room for the unexpected.  It is the same concept as not planning projects with a lot of overtime already factored into the effort when you have a limited staff.  This would not allow any overtime to catch up, or handle tasks that were inadvertently omitted from the project plan.  It is also important to leave some room for scope changes, as more is known about the project.    

                     Figure 6: SRO Project Estimate Productivity Comparison to Similar Projects

 

                  Figure 7: SRO Project Estimate Main Build Duration Comparison to Similar Projects

 

                           Figure 8: SRO Project Estimate MBI Comparison to Similar Projects 

GPA Project Validation and Risk Assessment

Figures 9 and 10 illustrate the validation of a vendor estimate.  The GPA project validation estimate was created using a PI for the MB Phase based upon the three projects highlighted in Figure 1, of similar size and  type that were completed by the same development team. The MB phase was considered reasonable.  However, the vendor estimate had a Planning Phase duration of 3.5 months and an Analysis (detailed requirements and high-level design) Phase duration of 3.5 months, running consecutively with no overlap of the MB phase.  This was actually done because the customer wanted Planning and Analysis completed within 3.5 months.  This project was 8154 FP's or 430K ESLOC.  My historical project data showed that projects of similar size, type, and development team, normally required a Planning duration of 26% of the time required to complete MB, and an Analysis duration of 48% of the time required for MB.  

Figure 9 illustrates that the GPA vendor estimate Planning phase duration is faster than 84% of all similar projects and twice as fast (3.5 months versus 7 months) as the GPA validation estimate, based on the development team's historical project data.  Figure 10 illustrates the same trend; that is, the GPA vendor estimate Analysis phase duration is faster than 84% of all similar projects and twice as fast (4 months versus 8 months) as the GPA Validation Estimate. Also, 75% of the Planning phase normally overlaps the Analysis phase and 68% of the Analysis phase normally overlaps the MB phase.  Planning the project with Planning and Analysis phases of only 3.5 months with no overlap of MB, would indicate a High Risk for completion within a 3.5-month time frame.  

This was discussed with the customer and vendor.  It was determined that the Planning and Analysis Phases would be planned based upon historical project data.  The PM developed a risk mitigation strategy such that detailed design could still begin within 3.5 months, which was the primary concern and the reason that the Planning and Analysis phases were being cut short in the first place.  This was done by using an iterative development methodology; that is detailed design could begin on each module as soon as the detailed requirements (Analysis) were completed for that module.

                         Figure 9: GPA Project Planning Phase Validation and Risk Analysis

                      Figure 10: GPA Project Analysis Phase Validation and Risk Analysis

Conclusion

The one thing that "planning by the numbers" and "painting by the numbers" do have in common is that you must have the numbers in order to start.  It is extremely important to collect internal historical project data, which is a critical success factor for the PBN process.  Using the premise of discovery metrics, where we discover facts about our world and use those discoveries, we are better prepared to deliver successful software projects. [7]

At a conference several years ago, I heard a parable that is particularly appropriate.  It goes like this: There were two hunters who chartered a pontoon plane to take them moose hunting near a lake in Alaska.  The pilot told them as he dropped them off: "I'll pick you up in one week, but you can only bring one moose on the plane, due to the weight limit."  A week later, the hunters were waiting and had two moose.  The pilot exclaimed: "I specifically told you that you could only bring one moose on the plane!" To which the hunters replied: "We know, but the pilot last year let us bring two moose."  Not to be outdone, the pilot reluctantly agreed; so they stuffed the two moose aboard.  The plane took off, barely clearing the trees on the other side of the lake, and then "BAM", they hit the middle of a mountain.  It was a mess, but luckily everyone survived.  As the hunters pulled themselves up off of the ground, they looked at each other and said: "Well, at least we made it further up the mountain than we did last year!"  The moral of this parable is to stop running into mountains with your software projects.  By learning from the past, you too can "save the world one project at a time."

References

[1] Michael Mah, "Sizing Up Your Promises and Expectations," IT Metrics Strategies, Cutter Information Corp., September 2000.

[2] Michael Mah, "IT Organization, Benchmark Thyself," IT Metrics Strategies, Cutter Information Corp., March 2000.

[3] Michael Mah, "IT Organization, Benchmark Thyself [Part 2]," IT Metrics Strategies, Cutter Information Corp., April 2000.

[4] Robert C. Tausworthe, "The Work Breakdown Structure in Software Project Management," The Journal of Systems and Software, 1980.

[5] Lawrence H. Putnam and Ware Myers, "Measures for Excellence", Yourdon Press, 1992.

[6] Lawrence H. Putnam and Ware Myers, "Industrial Strength Software", IEEE Computer Society Press, 1997.

[7] Jim Mayes, "Achieving Business Objectives II: Building a Software Metrics Support Structure," IT Metrics Strategies, Cutter Information Corp., June 2000.

[8] Jim Mayes, "Achieving Business Objectives: Balancing Time, Cost and Quality," IT Metrics Strategies, Cutter Information Corp., March 2000.

Return to Top